I need to specify an approach for migrating a Windows 2008 Active Directory environment to a new data centre. There is not currently connectivity between the two data centres though that could be an option if needed.
I am looking for the most sensible approach here. A limited amount of downtime will be acceptable, but this should be limited to hours rather than days.
Current options I have looked at are:
- Adding new DCs in the new Data Centre to the existing domain (with appropriate connectivity) and allowing replication, then decom old servers.
- Take a backup and restore this in the new Data Centre, but base don my reading this uses a system backup and so would probably not work if restored to a new machine?
Appreciate your help with this one.
Thanks